Printer Friendly Version

Project Engineering & Construction

 

The various infrastructure projects in this section include major roads, water, storm, sanitary, reservoirs, bridges and detention ponds. 

 

The major projects for 2011 are outlined in pdf icon 2011 Major Projects and include:

 

New Development Road Improvements

  • West QEII Business Park (N36) Phase 1 - Intersection and Divided Arterial Roadway

Road, Sidewalk & Pathway Improvements

  • 32 Street Sidewalk Improvements (57 Avenue - 30 Avenue)
  • Bower Neighbourhood Trail Upgrade

Road Capacity Improvement

  • 32 Street Local Improvements - Intersection Improvements & Widening and Roadway Reconstruction (Spruce Drive to 40 Avenue)
  • 67 Street Corridor Improvements - Study & Design 2009, Golden West / Orr Drive Improvements in 2010

Greater Downtown Action Plan (GDAP) - Traffic Initiatives

  • Realign 55 Street West of Gaetz Avenue (R25) (by WTP)
  • Gaetz Avenue Revitalization from 46 Street to 52 Street

New Subdivision Development

  • Queen's Business Park - Industrial - Phase 1 and 2
  • Timberlands Phase 1 - Commercial
  • Garden Heights (SW 27) - Residential
  • Michener Affordable Housing
  • Riverlands

Utility Off-site Levies

Water:

  • NW Industrial NE36, SE36, NE25 (53-54)
  • NHC Water Crossing on Riverside Drive
  • 39 Street - Water Trunk Twinning (from Mountview reservoir to Maxwell Avenue)

Sanitary:

  • Riverside Drive Trunk Twinning - Civic Yards to WWTP (Contract B)
  • Northwest Industrial - South "1B" Basin (45-67, 67-68) (Design in 2010 & Construction in 2011)
  • Northwest Industrial Development (NW 36) On-site Trunks (64-66); Extension & Off-site Trunk (60-59) On-site Trunks (65-66)
  • NHC (EHN) Northland Drive Sanitary Trunk - River to 30 Avenue
  • Vanier East & North - Sanitary Trunk (44-45)

Storm:

  • East Hill Central - North of 67 Street (SW27) - Pond D8 + Trunk (77-23)
  • EHC - Timberstone (SW23) - West Trunk (61-60) + Pond D2 & East Trunk (61-62)
  • EHC - 67 Street - Storm Trunks (NW22) & Pond D7
  • NHC - NW Annexation - Northland Drive from Gaetz Avenue to 78 Street Crescent. Oversize to accommodate are NW of Highway 11A / Highway 2A Intersection
  • NHC (EHN) - Northland Drive Storm Trunk & Pond at River from River to 30 Avenue (81-78)
  • Vanier East & North - Trunks (100-101) & Pond C8        

North Highway Connector Projects

  • North Highway Connector (NHC) - Phase 1A - Includes design, land acquisition, approches & work by outside agencies