The various infrastructure projects in this section include major roads, water, storm, sanitary, reservoirs, bridges and detention ponds. 

 

The major projects for 2012 are outlined in pdf icon 2012 Major Projects and include:

 

New Development Road Improvements

  • 19 Street (30 Ave to 20 Ave) - 4 Lane - 30 Ave to Quarter line in '13

Road, Sidewalk & Pathway Improvements

  • 32 St Sidewalk Improvements (57 Ave to 30 Ave)
  • Taylor Drive (60 St to Hamilton Dr - East side)
  • Ross St Sidewalk Improvement (46 Ave to 30 Ave)

Road Capacity Improvement

  • 32 St improvements - Intersection Improvements & Widening and Roadway Reconstruction (Spruce Dr to 40 Ave) Detailed Design '09 & Construction '12
  • Taylor Drive Pathway - South of Delburne Road

Greater Downtown Action Plan (GDAP) - Traffic Initiatives

  • Realign 55 Street West of Gaetz Avenue (R25) (by WTP)
  • Gaetz Avenue Revitalization from 46 Street to 52 Street (Phase 2)
  • Taylor Drive / Alexander Way Intersection Improvements (R15)
  • Taylor Drive / Ross Street Intersection Improvements (R16)

Subdivision Development

  • Queen's Business Park - Industrial - Phase 1 and 2
  • Timberlands Phase 1 - Commercial
  • Garden Heights (SW 27) - Residential - Phase 1
  • Michener Affordable Housing - Residential
  • Riverlands - Commercial

Utility Off-site Levies

Water:

  • NW Industrial NE 36, SE 36, NE 25 (53-54)
  • 39 St - Water Trunk Twinning (from Mountview Reservoir to Maxwell Ave)

Sanitary:

  • Northwest Industrial - South "1B" Basin (45-67, 67-68). Design in '10 & Construction in '11
  • NHC (EHN) Northland Drive Sanitary Trunk, River to 30 Ave
  • Vanier East & North - Sanitary Trunk (44-45)

Storm:

  • East Hill Central - North of 67 Street (SW27) - Pond D8 + Trunk (77-23)
  • EHC - 67 Street - Storm Trunks (NW22) & Pond D7
  • NHC (EHN) - Northland Drive Storm Trunk & Pond at River from River to 30 Avenue (81-78)
  • Vanier East & North - Trunks (100-101) & Pond C8        

North Highway Connector Projects

  • North Highway Connector (NHC) - Phase 1A - Northland Drive / 30 Ave Extension (Gaetz Ave to 67 St) - includes Engineering for 1A & 1B, utility relocates, land acquisition for rights of way, embankments, roadway drainage & construction of wildlife crossing

Local Improvements

  • Sullivan Quarter Servicing (Water/Sanitary)
  • Riverview Park / Heritage Ranch Servicing (Water/Sanitary)