Latest Project News

Sign-up for Servus Arena Project alerts RSS Feed Email

Downtown Arena Project - December 2016 Update

November 28, 2016 11:42 AM

Over the next month, crews are working on:

  • Completing foundational walls
  • Constructing walls for the players box and penalty box
  • Installing insulated precast walls and precast walls for elevator shaft
  • Installing structural steel
  • Constructing the loading dock