Servus Arena Project - August 2017

July 28, 2017 3:03 PM

The Servus Arena is now nearly fully enclosed and windows are installed. Most work is currently happening inside the new arena, with the following activities happening over the next month:

  • Structural installation and mechanical rough-in for concession area
  • Elevator installation
  • Pipe insulation and ductwork installation in lobby
  • Rink slab piping installation, reinforcing and inserts
  • Painting doors and frames, exposed steel and main corridor wall
  • Refrigeration room equipment and piping installation
  • Sprinkler installation
  • Arena concrete floor is being poured August 9-12. There will be an increase in truck traffic going to and from the arena during this period.