Latest Project News

Sign-up for Servus Arena Project alerts RSS Feed Email

Servus Arena Project - June 2017 Update

June 9, 2017 10:46 AM

Over the next month, crews are working on the following:

  • Starting door slab installation
  • Completing exterior glass installation
  • Grading for arena floor
  • Constructing the north entry vestibule
  • Completing the installation of curved panels
  • Installing arena lights
  • Completing insulation spray over seating bowl
  • Continuing to install masonry block and drywall
  • Painting

If you have any questions about the Servus Arena Project, please contact rpc@reddeer.ca