Work happening from August 14-27:

  • Paving – schedule is weather dependent
  • Wednesday, August 19 – paving from 45 Avenue to the bridge and on 46 Avenue (tentatively)
  • Thursday, August 20 – paving north lanes from 42 Avenue to the bridge (rotating intersection closures at 42A Avenue and 45 Avenue, signage and flag people will be on site to direct traffic)
  • Friday, August 21 - paving south lanes from 42 Avenue to the bridge (rotating intersection closures at 42A Avenue and 45 Avenue, signage and flag people will be on site to direct traffic
  • Paving the new multi-use pathway
  • Line painting on 55 Street and 46 Avenue
  • Landscaping on both sides of 55 Street
  • EL&P working to re-install light standards and traffic lights
  • 46 Avenue – curb and gutter pouring happening August 14 and 15 and curing is happening August 15, 16, 17 and 18

Detours and Road Closures:

  • On Thursday, August 20 and Friday, August 21 the intersection of 45 Avenue/55 Street will open early in the day, then close as paving crew approach. The 42A Avenue/55 Street intersection will open after the paving crew has passed. Flag people will be on site directing traffic to the open intersection
  • 46 Avenue from 55 Street to 53 Street is closed until August 21 (tentatively), weather dependent
  • 55 Street from 48 Avenue to 42 Avenue is completely closed until September 1
  • Michener Hill closed until September 1

Questions: