Happening July 31-August 6, 2015

July 31, 2015 2:09 PM

Work from 48 - 46 Avenue:

  • Adding gravel, concrete and pressure testing
  • EL&P working on their infrastructure

Work between 46 Ave and 42 Avenue:

  • Installing new catch basins on 46 Avenue and 45 Avenue
  • Installing retaining walls
  • Adding concrete on the south side of 55 Street s
  • Landscaping work beginning
  • Paving (bottom lift) starting at the bottom of Michener Hill to 42A

Road Closures and Detours

  • On Tuesday, August 4 the 42A Avenue intersection will open and the 45 Avenue intersection will close. The 42A Avenue intersection will be controlled as a 3-way stop.
  • 55 Street from 48 Avenue to 42A Avenue is completely closed. 
  • The Michener Hill will open for transit use only.