Construction Season Alerts

Happening September 9 to 20, 2016

September 9, 2016 10:52 AM

Happening September 9-20, 2016:

  • Relocating utilities as needed.
  • Landscaping in the centre of the roundabout, including concrete staining, rock placement and tree planting.
  • Connecting Carrington Drive to the new 30 Avenue extension and roundabout. Crews are constructing curbs and gutters, line painting and installing traffic lights.
  • Ongoing path construction.

Detours and Road Closures:

  • Carrington Drive at 30 Avenue remains closed until late-September 2016. Access into Clearview Ridge and Clearview Market is from Carleton Avenue, and Carrington Drive at 67 Street. All businesses are open during construction.
  • Walking paths around the former 67 Street and 30 Avenue curve is closed. Pedestrian detour signs are in place.


If you have any questions, comments or concerns please call 403-342-8158, or email