Construction Season Alerts

67 Street Johnstone Drive roundabout project update

September 12, 2017 3:30 PM

Update for September 12, 2017

Construction of the 67 Street and Johnstone Drive/Orr Drive roundabout and surrounding roadways is to be completed this year. This includes the following:

  • Road reconstruction on 67 Street, between Golden West Avenue and the roundabout (complete)
  • Paving on parts of 66 Street, Orr Drive, Johnstone Drive and 67 Street (complete)
  • Permanent pavement markings
  • Permanent street lighting
  • Asphalt trails
  • Landscaping of boulevards and roundabout circles

Happening next two weeks (Sept. 11, 2017 to Sept. 23, 2017)

  • Beveling and sealing joints in concrete paving
  • Permanent pavement markings
  • Asphalt trails on 67 Street and Edgar Industrial Drive
  • Barrier protection for overhead sign on 67 Street
  • Landscaping on 67 Street roundabout
  • Landscaping for North Ditch between Johnstone Drive and Golden West Avenue
  • Erect new street lighting on 67 Street

Road closures and detours

  • There will be intermittent lane closures to accommodate beveling and sealing joints and line markings.

Who do I contact for more information?

We are available by phone and email, and encourage businesses and residents to ask us questions or pass along comments. Residents and businesses who have questions or concerns during construction should contact The City at 403-342-8158 or constructionseason@reddeer.ca