Latest Project News

Sign-up for Servus Arena Project alerts RSS Feed Email

Downtown Arena Project - January 2017 Update

January 17, 2017 9:28 AM

This month, crews are:

  • Installing temporary gas lines
  • Installing structural steel
  • Tarping in and heating areas of the new building to prepare for under slab mechanical and electrical work

January 2017 Red Deer Arena Construction ProgressJanuary 2017 Red Deer Arena Construction Progress 2

If you have any questions about the Downtown Arena Project, please contact rpc@reddeer.ca